Skip to main content

ESIG - Accelerating the Integration of Variable Generation into Utility Power Systems

  • Members Area
  • About
    • Energy Systems Integration
    • Leadership Team
    • Board of Directors
    • Advisory Council
    • Newsroom
    • ESIG Excellence Awards
  • Blog
  • Resources
    • ESIG Reports/Briefs
    • Past Webinars
    • Past Workshop Presentations
    • Resource Library
    • Quick Reference Guides
    • IEEE Power & Energy Contributions
  • Membership
    • Current ESIG Members
    • Become a Member
    • Member Benefits
    • Student Memberships
    • Mentoring Program
    • Membership Referral
  • Working / Users Groups
    • Task Forces
    • Large Loads Task Force
    • Distributed Energy Resources (DER) Working Group
    • Operations and Maintenance (O&M) Users Group
    • Reliability Working Group
    • Research & Education Working Group
    • System Operation & Market Design Working Group
    • System Planning Working Group
    • GETs User Group
    • Probabilistic VRE Forecasting and Markets User Group
  • Contact
  • Events
    • Upcoming Events
    • Past Events
    • Sponsorship Opportunities
  • Join
  • Login

There are more than 8,000 interconnection requests in the United States today, largely renewable energy projects, with potential generation surpassing the combined peak demand in the lower 48 U.S. states. Interconnection studies are performed to determine whether a new resource could overload the existing transmission infrastructure in a given location. Today, interconnection studies have a short-term focus, performed on a small set of new projects and focused on least-cost transmission upgrades that would ensure reliability over a short (five-year) horizon.

Click Here to Download Study

However, the continued growth of large-scale renewables requires longer-term transmission planning to identify transmission upgrade options that have the largest net benefits over longer time horizons of 10 to 20 years. To bridge the gap between the short-term focus of current interconnection processes and long-term transmission needs, a more proactive generation interconnection process is needed. A more proactive approach can involve (1) increasing the number of projects in an interconnection cluster study, by increasing either the window of time or the geographical area considered, and (2) improving coordination of the Affected Systems Study (AFS) process.

This study by the Brattle Group examined three levels of proactiveness and calculated the average cost of interconnection for each. Using the Southwest Power Pool (SPP) and Midcontinent Independent System Operator (MISO) regions as a case study, the study assessed (1) a lower level represented by common practices today of studying generation interconnection on an annual or semi-annual basis, (2) a medium level represented by a three-year study window, and (1) a higher level represented by the five-year window used by the SPP/MISO Joint Targeted Interconnection Queue (JTIQ) study.

The study found that increasing the proactiveness of the generation interconnection process, by lengthening the time horizon, lowered costs. The lower level of proactiveness studied showed $117/kW, the medium level of proactiveness showed $98/kW, and the higher level of proactiveness showed $58/kW. In addition to having the lowest interconnection costs, the higher level of proactiveness (JTIQ) quantified adjusted production cost benefits of $34/kW. The results showed that proactive generation interconnection planning can help bridge the gap between short-term generation interconnection studies and long-term transmission planning studies while reducing interconnection costs significantly.

 

 

 

 

Quicklinks

  • Member’s Area
  • Join ESIG

Contact

704-473-0135

PO Box 2787
Reston, Virginia
20195 USA

info@esig.energy

Follow Us!

Follow Us on FacebookFollow Us on TwitterFollow Us on LinkedInFollow Us on YouTube
This form needs Javascript to display, which your browser doesn't support. Sign up here instead

Special Thanks To Our Sustaining Members

© 2025 ESIG. All Rights Reserved
Custom Site by VIEO Design